The National Highways Authority of India (NHAI) is the nodal agency of Ministry of Road Transport and Highways (MORT&H), Government of India and has been entrusted Construction of 4-Lane Greenfield Jalbehra Shahbad Section of NH-152G Start from KM 0+000 to KM 22+850 (Part of Shahbad-Thol Feeder Route) in the State of Haryana on Hybrid Annuity Mode Under Bharatmala Pariyojana Phase-l.
Description of Project Highway
The project falls in the State of Haryana for “Construction of 4-Lane Greenfield Jalbehra Shahbad Section of NH-152G Start from KM 0+000 to KM 22+850 (Part of Shahbad-Thol Feeder Route) in the State of Haryana on Hybrid Annuity Mode Under Bharatmala Pariyojana Phase-l”. In this section the alignment starts from Jalbehra Village, District- Kurukshetra runs through villages Thaska Miraanji- Jalbehra, Taska Miranji- Megha Majra, Rohti, Jhansa, Jharauli khurd, Kalsani-Mammon Majra, Sulkani- Shahzadpur and ends at Shahbad on Saha road. The Highway alignment crosses the existing Highway at design Ch. 18+565.
In this Section the alignment also crosses the following state highways
1. At Km 18+565 (SH-31)
Villages and Towns
The project Highway is a green field alignment passing through villages Thaska Miraanji- Jalbehra, Taska Miranji- Megha Majra, Rohti, Jhansa, Jharauli khurd, Kalsani-Mammon Majra, Sulkani- Shahzadpur in the State of Haryana (Length 22.85 km). The land use pattern of the project alignment is mainly agricultural and human habitation.
Intersections
The project highway crosses the following National Highways:
1. At Km 0+000 (NH-152)
2. At Km 22 (NH-44)
Existing Right of Way
The project highway crosses the following National Highways:
1. At Km 0+000 (NH-152)
2. At Km 22 (NH-44)
Cross Drainage Structures
Following are the new structures in the project corridor:
⮚ Major and minor bridges across rivers, streams, and canals Box Culvert
⮚ Hume Pipe Culverts
Existing Geometry and Junctions
- Truck Lay Byes: The project is a Green Field project hence there is no existing Truck Lay bye on the Project Highway.
- Toll plaza: The project is a Green Field project hence there is no existing Toll Plaza on the Project Highway.
- Bus Bays: The project is a Green Field project hence there is no existing Bus bye on the Project Highway.
- Major bridges: The project is a Green Field project hence there is no existing Major Bridges on the Project Highway.
- ROB: – The project is a Green Field project; Hence there is no ROB on the Project Highway.
- Minor bridges: There are 3 no. Minor bridges on the existing alignment which are to be widening as per concession agreement.
- Culverts: The project is a Green Field project hence there is no existing culverts on the Project Highway.
- Utility Services: -There are utilities like Transformer, Electrical Pole and HT line running parallel and crossing the project road which influence the development of the project area, need to be shifted. In addition, there is the presence of other important structures.
Project Benefits
The NH-152G project in Haryana has several purposes, including:
- Economic development: The project will help the economy of the region by providing employment opportunities, improving transportation, and strengthening tourism.
- Reduced travel time: The project will reduce travel time by connecting NH-152 with NH-44.
- Improved road quality: The project will improve the quality of the road, which will reduce the cost of operating vehicles.
- Improved air quality: The project will improve air quality through compensatory and roadside plantation.
- Better transportation facilities: The project will provide better transportation facilities.
Salient Features of Project
Project Details | Information |
---|---|
Name of the Project | Construction of 4 Lane Greenfield Jalbehra Shahbad Section of NH-152G Start from Km 0+000 to Km 22+850 (Part of Shahbad –Thol Feeder Route) in the state of Haryana on Hybrid Annuity Mode under Bharatmala Pariyojana phase –I |
Length of Project | 22.85 Km |
NH No. | 152G |
Name of Client | National Highways Authority of India |
Concessionaire | M/s. Ceigall Jalbehra Shahbad Greenfield Highway Private Limited |
EPC Contractor | M/s. Ceigall India Limited |
Independent Engineer | M/s MSV International Inc. in association with M/s MSV International Tech Pvt. Ltd. |
Letter of Award (LOA) | 02-June-2022 |
Date of Agreement | 12-December-2022 |
Appointed Date | 02-June-2023 |
Construction Period | 24 Months (730 days) from AD |
Schedule Completion Date | 31-May-2025 |
Bid Project Cost (Rs. in Cr) | Rs 684.00 Cr. |
Concession Period | 15 Years after commencing COD |
IE Mobilization Date | 23-May-2023 (As per NHAI Letter) |
Interchange | 01 Nos |
Major Bridges | 01 Nos |
Minor Bridge Cum LVUP | 01 Nos |
VUP/LVUP/SVUP | (VUP-01) + (LVUP-7) +(SVUP-10) |
Box Culverts | 23 Nos |
Pipe Culverts | 21 Nos |
Milestone-I (Days/Date) | 180 Days / 27-November-2023 |
Milestone-II (Days/Date) | 360 Days / 26-May-2024 |
Milestone-III (Days/Date) | 540 Days / 22-November-2024 |
Schedule Completion (Days/Date) | 730 Days / 31-May-2025 |
Project Technical Details (Scope)
1. Details of Length (Highway)
Sr. No. | Type of Cross-section | Total Highway Length (m) |
---|---|---|
1 | New Realignment & Bypass Roads | 22850 |
2 | Loops/Ramps | 2310 |
3 | Connecting Roads (Main Highway / Interchange location) | 679.5 |
2. List of Structures
Sr. No | Particulars | Unit | Number as per CA |
---|---|---|---|
1 | Pipe Culverts | Nos. | 21 |
2 | Box Culvert | Nos. | 23 |
3 | SVUP’ s | Nos. | 10 |
4 | LVUP’s | Nos. | 7 |
5 | VUP’s | Nos. | 1 |
6 | Minor Bridge Cum LVUP | Nos. | 1 |
7 | Minor Bridge (Widening) | Nos. | 3 |
8 | Interchanges | Nos. | 2 |
9 | Major Bridges | Nos. | 1 |
10 | Flyover | Nos. | 2 |
11 | Structures on loop and ramp | Nos. | 2 |
3. Toll Plaza
Interchange No. | Chainage | Toll Plaza | Location | Direction (Entry: to highway, Exit: from Highway) | No. of toll lanes (ETC+ Extra Wide) | |||
---|---|---|---|---|---|---|---|---|
On Main Carriageway | 5+077 | TP-1 | On Main Carriageway | Entry | 4+2 | |||
Exit | 4+2 |