Projects

The National Highways Authority of India (NHAI) is the nodal agency of Ministry of Road Transport and Highways (MORT&H), Government of India and has been entrusted Construction of 4-Lane Greenfield Jalbehra Shahbad Section of NH-152G Start from KM 0+000 to KM 22+850 (Part of Shahbad-Thol Feeder Route) in the State of Haryana on Hybrid Annuity Mode Under Bharatmala Pariyojana Phase-l.

Description of Project Highway

The project falls in the State of Haryana for “Construction of 4-Lane Greenfield Jalbehra Shahbad Section of NH-152G Start from KM 0+000 to KM 22+850 (Part of Shahbad-Thol Feeder Route) in the State of Haryana on Hybrid Annuity Mode Under Bharatmala Pariyojana Phase-l”. In this section the alignment starts from Jalbehra Village, District- Kurukshetra runs through villages Thaska Miraanji- Jalbehra, Taska Miranji- Megha Majra, Rohti, Jhansa, Jharauli khurd, Kalsani-Mammon Majra, Sulkani- Shahzadpur and ends at Shahbad on Saha road. The Highway alignment crosses the existing  Highway at design Ch. 18+565.

In this Section the alignment also crosses the following state highways

1. At Km 18+565 (SH-31)

Villages and Towns

The project Highway is a green field alignment passing through villages Thaska Miraanji- Jalbehra, Taska Miranji- Megha Majra, Rohti, Jhansa, Jharauli khurd, Kalsani-Mammon Majra, Sulkani- Shahzadpur in the State of Haryana (Length 22.85 km). The land use pattern of the project alignment is mainly agricultural and human habitation.

Intersections

The project highway crosses the following National Highways:
1. At Km 0+000 (NH-152)
2. At Km 22 (NH-44)

Existing Right of Way

The project highway crosses the following National Highways:
1. At Km 0+000 (NH-152)
2. At Km 22 (NH-44)

Cross Drainage Structures

Following are the new structures in the project corridor:
⮚ Major and minor bridges across rivers, streams, and canals Box Culvert
⮚ Hume Pipe Culverts

Existing Geometry and Junctions

  • Truck Lay Byes: The project is a Green Field project hence there is no existing Truck Lay bye on the Project Highway.
  • Toll plaza: The project is a Green Field project hence there is no existing Toll Plaza on the Project Highway.
  • Bus Bays: The project is a Green Field project hence there is no existing Bus bye on the Project Highway.
  • Major bridges: The project is a Green Field project hence there is no existing Major Bridges on the Project Highway.
  • ROB: – The project is a Green Field project; Hence there is no ROB on the Project Highway.
  • Minor bridges: There are 3 no. Minor bridges on the existing alignment which are to be widening as per concession agreement.
  • Culverts: The project is a Green Field project hence there is no existing culverts on the Project Highway.
  • Utility Services: -There are utilities like Transformer, Electrical Pole and HT line running parallel and crossing the project road which influence the development of the project area, need to be shifted. In addition, there is the presence of other important structures.

Project Benefits

The NH-152G project in Haryana has several purposes, including:

  • Economic development: The project will help the economy of the region by providing employment opportunities, improving transportation, and strengthening tourism.
  • Reduced travel time: The project will reduce travel time by connecting NH-152 with NH-44.
  • Improved road quality: The project will improve the quality of the road, which will reduce the cost of operating vehicles.
  • Improved air quality: The project will improve air quality through compensatory and roadside plantation.
  • Better transportation facilities: The project will provide better transportation facilities.

Salient Features of Project

Project DetailsInformation
Name of the ProjectConstruction of 4 Lane Greenfield Jalbehra Shahbad Section of NH-152G Start from Km 0+000 to Km 22+850 (Part of Shahbad –Thol Feeder Route) in the state of Haryana on Hybrid Annuity Mode under Bharatmala Pariyojana phase –I
Length of Project22.85 Km
NH No.152G
Name of ClientNational Highways Authority of India
ConcessionaireM/s. Ceigall Jalbehra Shahbad Greenfield Highway Private Limited
EPC ContractorM/s. Ceigall India Limited
Independent EngineerM/s MSV International Inc. in association with M/s MSV International Tech Pvt. Ltd.
Letter of Award (LOA)02-June-2022
Date of Agreement12-December-2022
Appointed Date02-June-2023
Construction Period24 Months (730 days) from AD
Schedule Completion Date31-May-2025
Bid Project Cost (Rs. in Cr)Rs 684.00 Cr.
Concession Period15 Years after commencing COD
IE Mobilization Date23-May-2023 (As per NHAI Letter)
Interchange01 Nos
Major Bridges01 Nos
Minor Bridge Cum LVUP01 Nos
VUP/LVUP/SVUP(VUP-01) + (LVUP-7) +(SVUP-10)
Box Culverts23 Nos
Pipe Culverts21 Nos
Milestone-I (Days/Date)180 Days / 27-November-2023
Milestone-II (Days/Date)360 Days / 26-May-2024
Milestone-III (Days/Date)540 Days / 22-November-2024
Schedule Completion (Days/Date)730 Days / 31-May-2025

Project Technical Details (Scope)

1. Details of Length (Highway)

Sr. No.Type of Cross-sectionTotal Highway Length (m)
1New Realignment & Bypass Roads22850
2Loops/Ramps2310
3Connecting Roads (Main Highway / Interchange location)679.5

2. List of Structures

Sr. NoParticularsUnitNumber as per CA
1Pipe CulvertsNos.21
2Box CulvertNos.23
3SVUP’ sNos.10
4LVUP’sNos.7
5VUP’sNos.1
6Minor Bridge Cum LVUPNos.1
7Minor Bridge (Widening)Nos.3
8InterchangesNos.2
9Major BridgesNos.1
10FlyoverNos.2
11Structures on loop and rampNos.2

3. Toll Plaza

Interchange No.ChainageToll PlazaLocationDirection (Entry: to highway, Exit: from Highway)No. of toll lanes (ETC+ Extra Wide)
On Main Carriageway5+077TP-1On Main CarriagewayEntry4+2
Exit4+2